Currently, if you have an action template set up that has dependencies between the steps, the lag in between those steps isn't "created" in the predecessor column in gantt. This means that if you apply the template, the steps are properly offset, but if you have auto-scheduling turned on, and shift the dates, the plan will schedule the dates as soon as possible, removing the lag that was placed by the action template.