Ability to have 0 (Zero) days in a project timeline
complete
C
Colin Hunter
Currently the minimal time a task can take in Hive is 1 full day. There are tasks that don't take full days, they take partial days or we were used to listing them as 0 days in other software because they like only a few minutes. We'd like to be able to do this in Hive as well.
A workaround to get this requires using (FS-1) for the predecessor entries
Log In
Kelley Bunge
complete
M
Matt Sanders
Added this one to address the same need: https://hiveteams.canny.io/feature-requests/p/allow-different-units-for-durations