Currently the minimal time a task can take in Hive is 1 full day. There are tasks that don't take full days, they take partial days or we were used to listing them as 0 days in other software because they like only a few minutes. We'd like to be able to do this in Hive as well.
A workaround to get this requires using (FS-1) for the predecessor entries
Created by Andrew Naisawald
September 30, 2021